Re: Chain Carryforward PO

$
0
0

OK. This is clear and it si working. The problem arise when I do not de-commit the remaining fund reservation and I carryforward the the PO. The budget carried forward everything (as you pointed out also including the remaining of the fund reservation), but the remaning fund reservation has not been carried forward. That means that in year X+1 the budget is bigger thatn the commitment when they should be mandatory equal after the carried forward (I decided to carried forward the budget related to the commitments).