Hi Eli,
Thank you very much for your inputs.
Is there any possibility or workaround for multiple funds using for single project.
eg : Water project ---- Project WP,
Health project--- Project HP
Private sector project--- Project PSP.
Funds:
Fund1
Fund2
Fund3
The above these three projects are used by multiple funds(as said in my previous thread we have three Funds).
Every single project is used by multiple funds.
our requirement is to get the combination of each Fund and individual Projects wise details respectively like budget data, actual cost data, etc. like belwo
1. Fund1 + Project WP
2. Fund2 + Project WP
3. Fund3 + Project WP
same for other Projects also.
we are trying to map each WBS element as Funded Program.
request you to provide your inputs to map this.
thanks in advance.
Regards,