WBS is not interchangable with Project. In your scenario, it is just so obvious that you need to create one Project (which corresponds to the funded program) with three WBS's. In other words, in CJ20N (or CJ01), you build a 2-level hierarchy. That way the mapping to FM is a straightforward thing.
Regards,
Ming