Hi,
Please, make sure that in activity 'Define Activation of Availability Control' 9H is duly defined in FM area in question. Also, check the assignment of the strategy (Assign Tolerance Profiles and Strategy for Control Objects)...
Regards,
Eli
Hi,
Please, make sure that in activity 'Define Activation of Availability Control' 9H is duly defined in FM area in question. Also, check the assignment of the strategy (Assign Tolerance Profiles and Strategy for Control Objects)...
Regards,
Eli