I think i found the problem. as you said i checked the assignment of tolerance profile and strategy for control object and its been assigned properly. but when i try to go back the system give me the error that
"Select a valid derivation strategy for availability control ledger 9H"
and now when i compare the strategy assigned and the strategy created i found no error. whats been assigned has also been created in activity "Define Derivation Strategy for Control Objects" & "Define Derivation Strategy for Tolerance Profiles" but its not available for selecting in activity "Assign Tolerance Profiles and Strategy for Control Objects" When i press "f4" all i see there is a strategy "9HSAP000" and not the one being created in above mentioned activities.
how to fix this?
Regards,