Re: Budget exceeded when creating PO

$
0
0

Hi Mauro,

 

Hmmm... So, PR's commitment was reduced, but no commitment for PO was created, because of AVC, right? And FMN3N for PR does not give any results... What is the status of this PO, is it pending now?

I can suggest the following:

a) Eliminate PO

b) Run FM_DLOI for this PR

c) Run FMN3N for PR

d) Run FMAVCREINIT

e) Re-introduce PO

 

Regards,

 

Eli