Thanks Eli,
The customer requirement unfortunately is to use the pool components (funds in the cover group) sequentially.
I don't think that SAP can solve this, but we will prototype the cover eligibility to be sure
Do you know, how SAP decides which funding to use from the pool?
So if fund 1000 budget is exhausted, and fund 1000-01 and fund 1000-02 are in the cover pool, which of the available 2 funds budget is used and on what basis?
Also how is the budget made available - does SAP execute a budget transfer before using the budget from the pool?
Thanks
Aleksey