Re: Integration Materials Management (FMX1 by ME31K)?
Another idea? Do you happen to have workflow activated for EMF creation? If 'yes', please, check note 1240779 - FMRE: Integrating earmarked funds and contracts
View ArticleRe: Integration Materials Management (FMX1 by ME31K)?
...and by the way: did you define commitment plan at all?
View ArticleRe: migo 221 movement fm error
Dear Eli, We debugged the code, system checks if "Goods Issues can consume Reservation documents." According to debugging, as you said, system allows it. But prior to this control, system checks the...
View ArticleRe: migo 221 movement fm error
Where is the message issued? In CHECK_REFDATA_VORGN method? Could you please specify your current SAP release?PSM_FM_CORE_GEN should be normally cleared, unless something is changed with the release.
View ArticleNegative Budget
Dear Experts, Previous year we had negative budget but for the current year we have positive budget with the same combination i.e., Fund Center and Commitment Item. When we pass the entries with the...
View ArticleValidation For Period in FMCCA/FMCCD
Hello Colleagues, I need to create a validation by the period of the budget : Using FMCCA/FMCCD, I have these options : But the Budget line Period is returning only the value 16, I would need the...
View ArticleHow to Change Currency in Grant Master
HI Experts, We have uploaded the Grant Currency as USD instead of CAD. We have even released budget, then when we took reports in local currency we realized that the currency is not right. We have...
View ArticleRe: Validation For Period in FMCCA/FMCCD
Hi Eli, Thanks for your reply. I mean the "Month". In FMCCA when I use period ( FMKU_S_LINE-RPMAX) it's returing 16 only, the same value that is recorded on table FMBDT. I was expecting the values 1...
View ArticleRe: Validation For Period in FMCCA/FMCCD
Hi, OK. But, I cannot see where you have this restriction of '16'? If you put FMKU_S_LINE-RPMAX in pre-requisites you are free to enter whatever value you want. Regards, Eli
View ArticleRe: Validation For Period in FMCCA/FMCCD
Hi Eli, Thanks for your reply. Yes, These are the steps I am executing : - In FMCCA I enter FMKU_S_LINE-RPMAX = '1' and Budget period = 'M01'.- In FMBB I enter Month '1' - But During Posting in...
View ArticleRe: Validation For Period in FMCCA/FMCCD
What is your distribution key? It should be '0', I guess...
View ArticleRe: Validation For Period in FMCCA/FMCCD
Hi Eli, Thanks for your reply. The distribution Key was 1, I have changed to 0, but FMKU_S_LINE-RPMAX is still 16 during the validation even with the Month '1' in FMBB. Regards, Filipe Santos.
View ArticleRe: Validation For Period in FMCCA/FMCCD
Actually, on second thought, it makes sense. In FMBL table RPMAX is always set to '16' and distribution is done on columns like in total tables in SAP.
View ArticleRe: Integration Materials Management (FMX1 by ME31K)?
Hi Eli, You mean: define commitment plan for all contract types? Best regardsClaudio
View ArticleRe: Integration Materials Management (FMX1 by ME31K)?
No, I mean, when you create a contract, do you push on 'Commitment plan' button and tick the generation flag?
View ArticleRe: Validation For Period in FMCCA/FMCCD
Hi Eli, Thanks for your reply. So I think it's not possible to validate the Month in FMCCA or derive the Budget Period According to Month in FMCUDERIVSUB. Regards, Filipe Santos.
View ArticleRe: Validation For Period in FMCCA/FMCCD
It doesn't look like... at least, with standard tools. You can derive Budget period from posting data, but not from the 'period' field in FMBB as it is just an instruction to system where to put the...
View ArticleRe: Validation For Period in FMCCA/FMCCD
Hi Eli, Thanks for clarifying the issue. Regards, Filipe Santos.
View ArticleRe: How to Change Currency in Grant Master
Dear Omparkash, You can change the currency field to optional or ready for input in lifecyle field status of Grant Type, as shown in screenshot below: Hope this resolve the issue.Regards, Amar Lal
View ArticleRe: Integration Materials Management (FMX1 by ME31K)?
Hi Eli, Will be generation flag the field below in the filed status of contract (field generate commintent plan item)?I am asking you, because I looking for this field and I couldn't find it in screens...
View Article