Re: FMJ2 - Carry forward with budget Line

I don't quite understand. Budget document was not created? If not, please send screenshots for configuration you have done here;* Closing Operations - Enter default settings* Closing Operations for...

View Article


Re: Avaialability control is checked only if the assigned value is increased...

I found the answer. In customsing for Activate/deactivate available control Always Check - this check box should be checked to trigger AVC at every stage of document chain. Table V_FM01TOL_AVA field...

View Article


Re: Avaialability control is checked only if the assigned value is increased...

Thanks for update. I completely forgot about Former AVC settings.

View Article

Image may be NSFW.
Clik here to view.

Re: FMJ2 - Carry forward with budget Line

Hello, Avalability control is activated and I ma working with BCS Budget. In 2013 I have introduce my budget FMBB (Budget line). Then I have created a reserve agaisnt this budget line. When I try to do...

View Article

Re: FMJ2 - Carry forward with budget Line

Can you try and reconstruct AVC via FMAVREINIT? Also, can you check in FMBH table if budget document was created nevertheless?

View Article


Re: FMJ2 - Carry forward with budget Line

Hello Eli, I have run FMAVREINIT for both control ledgers. Adjustments have been done with sucess. When I execute again the FMJ2, the error is the same. No money enough in 2014. In table FMBH there is...

View Article

RIBs No information found

Good morning, I have customized all "revenue increasing budget" and later on I have completed transaction code FMRBDERIROR with origen and destiny of the RIBS:             Commitemnt item (revenues)+...

View Article

Re: FMJ2 - Carry forward with budget Line

Hi, In the first screenshot (IMG: Activate Budget Carryforward for Commitment), where you define flag for budget carry-forward, please distinguish between value types and enter the budget category....

View Article


Re: RIBs No information found

Hi, You have first to make sure that payment transfer is duly registered for the revenue document, which is supposed to be the source of budget for your expense address. Regards,Eli

View Article


Wrong committement item in PO - posted on behalf of Preeti K

Hi, User assigned wrong commitment item in PO,  so posted value is sitting in different fund center which is differ from PO.PO is done as stock transfer from one dept to other dept.  Now the user want...

View Article

Image may be NSFW.
Clik here to view.

Budget transfer from one commitment to other commitment in FMBBC

Dear Expert, We are facing an issue with transfer of budget from one one commitment item to other commitment item. below is the detail for commitment from where the budget needs to be transfer.  Now I...

View Article

Re: Budget transfer from one commitment to other commitment in FMBBC

Hi,Budget activities are fiscal year dependent,availability checked for 2014.

View Article

Re: Wrong committement item in PO - posted on behalf of Preeti K

Hi, Correct PO with t.code FMCN and FMCT to actual FC and CI.

View Article


Re: Budget control period wise as well as Year wise

We need to control the budget figures on monthly basis & residual balance of previous month data ,must be carry forward to next month up to financial year close. System wont allow any entries if it...

View Article

Re: Budget transfer from one commitment to other commitment in FMBBC

Hi abapers experts, any one get the solution...  We need to control the budget figures on monthly basis & residual balance of previous month data ,must be carry forward to next month up to...

View Article


Re: Budget transfer from one commitment to other commitment in FMBBC

Dear Rabin, Thanks for your reply. Budget activities are year dependent -- I agree. But why system doesn't consider last year carried foreword commitments against last year  carried forward budget as I...

View Article

Project Management and Financial Management

Hello, Our Federal client uses WBS for Inter-Agency Agreements.  They use a simple structure to collect costs and define budget availability at the WBS level.  They also have a need for a Project...

View Article


error: G/L account 64000xxx (expense) cannot be used (please correct)

hi Expert, i need to create purch.requisition doc with Fund Ctr.& Commitment Item in it.only got problem when trying to create requisition with account assignment A (asset) or K (cost center). the...

View Article

Re: error: G/L account 64000xxx (expense) cannot be used (please correct)

Hi Please check field status group for -the  error will pop up if there are any mismatch between the field status groups assigned to the GL account and the Fund Ctr.& Commitment Item.for respective...

View Article

Re: Reason for Budget Deficit in GMAVCOVRW

Hi: At last I was able to find the reason behind budget overrun in GMdespite of strict check.I first tracked the last document which consumed or committed thebudget for this sponsored class, program,...